Seawall improvement Olympic Harbour

Project description

Solution of problems of overflow in the seawall. Action in the submerged breakwaters with placing in his coronation of concrete blocks of 40 T. Building a “waves spits” in the coronation of concrete bleachers. Joint venture with the International Centre for Coastal Resources Research (CIIRC)-UPC.

Details
  • Seawall improvement against the swell overpass
Situation

Project data

  • Client: Barcelona City Council
  • End of design: 2010
  • Budget: 4.5 M€
  • Works done: Conceptual and construction design