Project description

Design and implementation of a system to regenerate the beach Es Través in Sóller (Mallorca) with the contribution of 16,000 T of sand. The system allows dumping of sand pumped from a transport vessel with a capacity of 6,000 T to the beach located 500 m from the anchor point of the boat. The system allows trucks without using circulating along the promenade.


16.000 T

Surface: 0,5 ha


Project data

  • Client: Castilla la Mancha Minera. Ministerio de Agricultura y Medio Ambiente
  • End of project: 2012
  • Budget: 0.7 M€
  • Works done: Project and works direction